Project Overview
As part of the City’s Watercourse Erosion Program, the City engaged the Toronto and Region Conservation Authority (TRCA) to restore the following stormwater outfall locations:
- Site 1: Closest Intersection – Castlemore Rd & Humberwest Pkwy
- Site 2: Closest Intersection – Castlemore Rd & The Gore Rd
- Site 3: Closest Intersection – Kennedy Rd & Derry Rd E
Over time, sediment buildup and plant growth affected the downstream ditches and upstream infrastructure at the outlet locations.
The completed restoration work included:
- Remove accumulated sediment and vegetation.
- Restored the sites to their original design to imrpove drainage, reduce erosion and support long-term performance of the stormwater system.
Project Timeline
Construction was completed in Spring 2026.
Project Map
Project Outcomes
Site 1: Castlemore Rd & Humberwest Pkwy
Site 2: Castlemore Rd & The Gore Rd

Site 3: Kennedy Rd & Derry Rd E