Creditview Road Bridge - 430m N of Steeles Ave W (over Credit River Tribute)


Last Updated: Tuesday, May 05 2020, 03:25
Project: Future Construction Project Under Design
Status: In Progress

Project Details​

This project includes the design of road bridge total replacement.

Project Status Update

  • ​The design work was 60% completed. There is a utility conflict which is being resolved prior to tender.
  • The structure is expected to be tendered in March 2020 (subjected to budget approval). The council authorization to begin procurement is pending.
  • Expected to start the construction in July 2020 and finish by November 2020.