Project: Park Walkway Improvement
Status: Complete

Park Walkway Improvement

Work on the Earnscliffe Park North and South Pedestrian Bridges includes, but is not limited to:

  • Remove and replace bridge superstructure
  • Saw cut and remove top of existing abutment and ballast walls
  • Form and pour new top of abutment and ballast walls
  • Install new approach guard rails and caisson piles
  • Install new threshold plates and elastomeric expansion joints
  • Repair existing gabion baskets
Project Status
  • Construction completed January 2018.