Project: Major Road Construction
Status: Complete
Project Details
This project consists of Züm improvements on Queen Street. It includes modification for the lane width, required upgrades to City utilities and Regional facilities, intersection improvements, new bus pads, bus bays and bus shelters, landscaping, traffic signals, street light system, storm sewer and watermain. For more information on Züm, click here.
Scheduling Details
Tender Date: April 30, 2009
Construction Start Date: July 6, 2009
Construction Substantial Complete Date: July 20, 2010
Construction Complete Date: July 27, 2010