Crocker Drive and Braydon Boulevard - At Chant Pond


Last Updated: Friday, Sep 27 2019, 03:41
Project: Stormwater Management Pond
Status: Complete

Project Details

This project consists of removing sediments and improving the stormwater management pond located near Crocker Drive and Braydon Blvd. The scope of work includes:

  • Excavation of all sediments in the pond
  • Temporary stockpiling and dewatering of the pond sediments
  • Offsite disposal of excavated sediment
  • Site restoration activities

Project Status

  • Construction commenced September 2018
  • Construction completed May 2019​