Birchbank Road - Dixie Rd to Avondale Blvd


Last Updated: Thursday, Apr 13 2017, 11:01
Project: Road Resurfacing
Status: Complete

Project Details

Residents will be advised through a Notice of Construction when to expect crews to start work on their street. The contract for this road resurfacing project was awarded to Furfari Paving Company Ltd.

For more information on the Road Resurfacing Program, contact Public Works at the City of Brampton at 905.874.2500.

Scheduling Details

Notice of Construction Delivered on: June 21, 2016
Construction Start Date: June 30, 2016
Construction End Date: September 2, 2016

Project Status Update

All work is complete.


Map it