Project: Stormwater Management Pond
Status: Complete

Project Details

This project consists of removing sediments and improving the stormwater management pond located near the intersection of Richgrove Drive and Latania Boulevard (Carberry Pond). The scope of work will include:
 
• Site preparation activities
• Excavation of all sediments in the pond
• Temporary stockpiling and dewatering of the pond sediments
• Offsite disposal of excavated sediment
• Site restoration activities
 
Scheduling Details
 
Tender Awarded in: July 2014
Construction Start Date: July 2015
Construction End Date: November 26, 2015
 
Project Status Update
  • Work is now complete.
  • Maintenance period has begun.

Map it