Harold Street - McLaughlin Rd to Fletchers Creek


Last Updated: Thursday, Oct 27 2016, 11:16
Project: Water Works
Status: Region of Peel

Watermain Replacement & Sanitary Sewer Repalcement
 
Watermain Scheduling Details
Anticipated Construction Start Date: September 23, 2013
Anticipated Construction End Date: February 24, 2014
 
Sanitary Sewer Scheduling Details
 
Anticipated Construction Start Date: December 16, 2013
Anticipated Construction End Date: February 26, 2014
 
Traffic Impacts
 
There will be traffic restrictions in the construction area. Residents will be notified at least one week in advance when the construction is close to their properties.
 
Project Status Update
 
  • Final road pavement reconstruction will take place in April - May (2014).
  • For more information regarding this Region of Peel sponsored project, contact 905-791-7800.​