Steeles Avenue (Züm) - Winston Churchill Blvd to Shoppers World Plaza Entrance


Last Updated: Thursday, Oct 27 2016, 11:16
Project: Major Road Construction
Status: Complete

Project Details

This project consists of the construction of Züm/Acceleride phase 2 installations along Steeles Avenue from Winston Churchill Boulevard to Shoppers World Plaza Entrance. The project will include the installation of eight major/minor station stops, installation of the City’s Transit Signal Priority (TSP), Emergency Vehicle Pre-Emption (EVP), and fibre infrastructure at 14 signalized mid-block intersections within the project limits.

Scheduling Details

Construction Start Date: August 5, 2014
Construction End Date: Fall 2015

Project Status Updates

  • The project is substantially complete.
  • The project is being monitored under two-year warranty.

Map it