McLaughlin Road - Harold St to Elgin Dr


Last Updated: Thursday, Oct 27 2016, 11:16
Project: Water Works
Status: Complete

Fletcher's Creek Trunk Sewer & Sanitary Sewer Construction

Scheduling Details
 
Construction Start Date: August 27, 2013
Anticipated Construction End Date: December 16, 2013
 

Traffic Impacts

There will be traffic restrictions in the construction area. Residents will be notified at least one week in advance when the construction is close to their properties.

Project Status Update 

  • Final road pavement reconstruction will take place in April - May (2014).
  • For more information regarding this Region of Peel sponsored project, contact 905-791-7800.