Small Business Inspections

Inspection services are provided for construction projects for various reasons, including:

  • Ensuring compliance with the health, safety and structural requirements of the Building Code and relevant by-laws
  • Ensuring construction is completed in accordance with the approved plans
  • To answer questions and guide the business owner or contractor in completing the construction project correctly

Please coordinate with the contractor about who will be requesting inspections.  If inspections are not requested at appropriate times, uncovering the construction will be required. 

Note: Once you have picked up your permit, please review all documents for changes that may have been made to the submitted drawings.  If any changes raise concern please review them with your plans examiner.

Along with permit drawings you will a receive permit card and the mandatory inspections, these are discussed in detail below.  On the same card you will find all required reports and certificates to be provided during the construction process. 

If a commitment form is filled out and signed, those professionals have committed to perform general reviews of the construction.  Please review these requirements with your inspectors.  Delays in submitting required documents can result in orders being issued and/or delaying of occupancy and/or closing the permit. 


Are You Ready for Inspection?

Please click on the appropriate category below to view the stages at which an inspection should be requested.  Remember the inspections required for your project will be indicated on your inspection list. 

Note: Please ensure that the permit drawings are kept on site at all times during construction and available during inspections

expandBuilding Inspections

Start of Construction

Purpose of this site meeting is to identify any questions the contractor has, if any, especially regarding notes from plans examiners (if not already done so during permit pick up) prior to construction.  Also reviewing required reports/certificates and fences to prevent hazardous condition to public.

Footing

At ready stage for pouring concrete, excavation complete, forms in place (or trench excavated) on undisturbed soil free of standing water, mud and loose earth

Backfill

Ready for backfilling of foundation, dampproofing applied, weeping tile covered with stone (min. 6 inches of cover)

Structural Framing

Prior to insulation but after rough ins are complete and passed (plumbing, hvac and electrical)

Fire Separations, Closures and Fire Stopping

Fire separations fully complete as per design details and/or listed systems

Interior Finishes

Interior finishes completed including but not limited to trim, paint and doors, normally done with occupancy and/or final inspection

Fire Alarm Systems

Fire alarm systems complete and verified and all paperwork ready to be submitted to the inspector, systems also ready to be tested in presence of the inspector

Sprinkler and Standpipe Systems

Sprinkler and/or standpipe systems complete, tested and paperwork ready to be submitted to the inspector, systems also ready to be tested in presence of the inspector

Emergency Lighting and Power

Emergency lighting and power systems complete, tested and paperwork ready to be submitted to the inspector, systems also ready to be tested in presence of the inspector

Fire Access Routes

Fire access route complete with reports confirming capable of supporting fire department’s equipment

Occupancy

Notice of completion must be submitted (NofC form) prior to occupying the newly constructed space or part of, once all applicable inspectors pass occupancy inspections an occupancy permit (sample) will be issued and mailed to owner within 5 business days

PUBLIC POOLS

Pool Deck, Dressing Rooms and Emergency stop systems complete and Pool form completed and ready for submission to inspector

Final

All construction is complete, interior and exterior. Once passed by all applicable inspectors a Certificate of Final Inspection will be sent within 10 business days

expandPlumbing Inspections

Start of Construction

Purpose of this site meeting is to identify any questions the contractor has, if any, especially regarding notes from plans examiners (if not already done so during permit pick up) prior to construction.  Also reviewing required reports/certificates and fences to prevent hazardous condition to public.

Fire Service Mains

 

Prior to backfilling

Outside Sewers

 

Prior to backfilling

Water Service

 

Complete with tracer wire, prior to backfilling

Underground Plumbing rough in

Water service, sanitary and storm drains before covering

Drains, Waste and Vents

 

Complete and ready for testing

Water Distribution System

Complete and ready for testing

Plumbing Fixtures and Appliances

Plumbing System (drains, supply and venting) installed and tested

Occupancy

Notice of completion must be submitted (NofC form) prior to occupying the newly constructed space or part of, once all applicable inspectors pass occupancy inspections an occupancy permit (sample) will be issued and mailed to owner within 5 business days

PUBLIC POOLS

Suction, gravity outlets and covers complete

PUBLIC POOLS

Circulation/re-circulation systems complete

Final

All construction is complete. Once passed by all applicable inspectors a Certificate of Final Inspection will be sent within 10 business days

expandHVAC Inspections

Start of Construction

Purpose of this site meeting is to identify any questions the contractor has, if any, especially regarding notes from plans examiners (if not already done so during permit pick up) prior to construction.  Also reviewing required reports/certificates and fences to prevent hazardous condition to public.

Building Envelope

Including but not limited to exterior cladding, insulation and vapour barrier

HVAC rough in

HVAC ductwork complete

Substantial Completion of HVAC Systems

Systems fully functional

Kitchen Exhaust Systems

Complete and Ready for testing

Fire Suppression Systems

Complete and Ready for testing

Occupancy

Notice of completion must be submitted (NofC form) prior to occupying the newly constructed space or part of, once all applicable inspectors pass occupancy inspections an occupancy permit (sample) will be issued and mailed to owner within 5 business days

Final

All construction is complete. Once passed by all applicable inspectors a Certificate of Final Inspection will be sent within 10 business days

If you have any questions, please contact your inspector in the specific discipline:  building, plumbing or HVAC inspector between 8 am and 9 am. Inspections take place between 9 am and 4 pm.  Inspection requests can be:

All inspection requests received before 3 pm will be scheduled for next business day.