Yard Improvements

​The City of Brampton is working on redeveloping its Public Works Yards to meet the future of Brampton's growth and service expectations.​​

Williams Parkway Works Yard

Williams Yard Concept Render

Conceptual Drawing of New Administrative Building

 

Redevelopment started in 2013 and includes:

Phase I - Completed May 2015

  • New office building
  • Storm water management pond
  • Two new entrances to access the yard

Phase II - Completed June 2017

  • Covered sand/salt handling and equipment storage facility
  • Road sign shop
  • Fleet maintenance bays and stores

Project Information

 

Sandalwood Parkway Works Yard

   Sandalwood Yard

Maintenance Bay at Sandalwood Yard

120 Sandalwood Parkway

Brampton, Ontario L7A 1L7

Redevelopment completed in 2010 included:

  • New office building
  • Covered parking garage
  • Indoor sand/salt storage and handling facility
  • Indoor service bays
  • Berm and fence to block noise and light
  • New entrance to the yard

Proposed Future Yards

The City of Brampton has proposed building two new additional yards. A Class Environmental Assessment was completed in 2012 to investigate the impact these yards would have on the environment. Further evaluation of yard development, design and funding requirements is currently underway.

Heritage Road & Steeles Avenue West
to service South-West Brampton
View the Conceptual Site Plan

Highway 50 & Cadetta Road
to service North-East Brampton
View the Conceptual Site Plan

​​